ATHOL – A new report from Building Inspector Bob Legare regarding the status and potential demolition of the York Theater shows that additional asbestos had been found.
In the York Theater, once the home of Lucky Lanes, Legare reported, “Tighe & Bond is currently conducting a Phase 2 environmental assessment of the bowling alley. Unfortunately, additional asbestos containing materials have been identified. These include roof patches, portions of the bowling ball return system and several areas of plaster patching.”
While asbestos wrapping of the boiler in the basement has previously been removed, as well as the oil tank, Legare said he has received no information indicating “any additional environmental concerns have been identified.
“Unfortunately, these additional findings continue to increase the potential project cost,” the report states. “Once we receive the basement inspection report, we can review the findings and determine what options are available moving forward.”
At a Nov. 10 meeting of the Select Board, member Mitch Grosky expressed concern that Legare’s report did not mention the adjacent York Building.
“I remember hearing we had to do something with the front of that building before winter, because there was a chance of it crashing in during the winter, at the first big storm, and we were talking about pushing that wall in,” he said. “Now, that seems to be completely stalled because there’s no mention of it here and we’re getting into winter.”
Peter Reynolds, president of McKenzie Engineering of Leominster, stated in a report from September that, due to lack of maintenance, water has damaged the roof and the resulting leaks have led to further damage to the two floors in the 8,000 square-foot structure. The first-floor framing couldn’t be inspected due to some four feet of water in the basement. In his opinion, “the structural capacity of the roof, the second and first floors have been severely compromised.”
Reynolds added that a collapse of the roof due to winter snow could result in portions of the building falling towards Main Street and endangering the public.
Town Manager Shaun Suhoski said the town was waiting for the results of environmental testing on the York Building.
Speaking to the Daily News on Nov. 20, Suhoski said, “As it seems with everything lately, the issue is more complicated than it appears on its face. This gist of it is, both the (town-owned) York Theater and the privately-owned York Building have asbestos-containing material. So, that’s impacting the nature of the scope of work that we can undertake.”
The town manager said contractors who may be interested in the demolition work “don’t want to give us a price unless it’s within a competitive bid, because they’d be bidding against themselves. So, we’re kind of in a bit of a Catch-22 at the moment.”
Suhoski explained that he and Legare have met and are putting together a proposal “to have an engineer put together a scope of work for bidding, and then we’ll go back to the board with that and see if we want to bid this, even knowing we may not have all the money secured.”
Rather than clearing any remaining asbestos from the buildings, they may have to be demolished with the asbestos intact. That means all of the demolition waste would have to be disposed of at a waste site that accepts asbestos-contaminated materials.
“That’s kind of the feedback Bob has gotten, but we’re waiting for the written reports,” said Suhoski. “We know various areas came back hot, and we’re just waiting for the written report on that, and the engineer will look at different options.”
Suhoski said the town has received word on a MassDevelopment Site Readiness Fund grant for demolition of the theater. The town, he said, applied for $300,000 for work on the York Theater. That amount, said Suhoski, would serve as a contingency to a $1 million federal request “that Congressman McGovern has put forward. But that’s stuck in the federal budget process, so we can’t count on that yet. We’re hoping those two sets of funds, together with some funds from our demolition account, would be enough.”
As for the York Building, “We have a court order to make things safe,” said Suhoski. “Town counsel will tell you that includes demolition. We need to find the owner just to make sure we’re protecting the town from liability.”
The York Building, owned by Jonathan Eldridge, has been the subject of recent legal action. In June, Housing Court Central Division Judge Timothy Sullivan found that Eldridge remains in contempt of previous court orders and that the property is a public nuisance.
“It’s a privately owned structure and the town may need to step in, but it’s not free,” Suhoski added. “But we’re looking for more grants and we’ll keep pressing forward.”